26 Jun 2024 12:31:33
I've heard from a good source that the reason for the delayed Copland building works is not from a delay in materials, but a delay from our side setting up payment. This was repeatedly asked for by the manufacturers and not set up. As soon as it was set up then the process began. This is the real reason of the delay.

Also the first 5 games due to be played at home will take place away. 2 qualifiers and 3 league games. We want Murrayfield as the increased ticket sales will cover any costs related to the move.


1.) 26 Jun 2024
26 Jun 2024 13:34:53
Working on large construction projects this is highly unlikely mate. Contracts like NEC4 are set well ahead of time with payment schedules and "damages" should parties renege on certain commitments. Also from previous suggestions last week that Rangers were ordering materials again isn't how these type of projects work.


2.) 26 Jun 2024
26 Jun 2024 13:36:35
Silly season with rumours on this topic, i think the rangers board are incompetent but even I don’t think they are capable of this Level of incompetence.


3.) 26 Jun 2024
26 Jun 2024 13:39:52
Agree 100% Karen too big a contract to not have in place pre start.


4.) 26 Jun 2024
26 Jun 2024 13:51:53
I'd assume that payment structure would've been agreed before work started but surely the lack info from our club is only fanning the flames for numerous stories we all read, come out Mr chairman tell the fans what is going on.


5.) 26 Jun 2024
26 Jun 2024 14:28:58
No foreign manufacturer would accept anything these days other than pro forma payment ex works . The delay may be shipping and the cause of delay, if that, would be down to buyer or shipper or both .


6.) 26 Jun 2024
26 Jun 2024 16:13:07
You are missing the point, of course payment schedules and structure WERE all agreed, but we failed to set up the agreed payment structure for the steel is what I’m told. Hence how the supply of the materials never proceeded until we did. Don’t shoot the messenger but the source is very in the know at board level.


7.) 26 Jun 2024
26 jun 2024 14:54:41
is that a serious request, walter? you actually wanting a company to tell the public if they’re internal business, why on earth would anyone do that? Did any other business give you an update every day of their building work and financial details?

they’re working on making ibrox better, why is there people who say they’re rangers fans fanning the flames of conspiracy, and that’s precisely what you're attempting to do.


8.) 26 Jun 2024
26 Jun 2024 15:12:42
Baffles me how Rangers fans openly come on here to fabricate money issues being the reason for the stadium delays knowing full well someone from the other side is going to run and run with this.


9.) 26 Jun 2024
26 Jun 2024 18:01:49
At the meeting held with the fans in March, Bisgrove told fans at that point they didn’t have planning permission agreed and had not signed with a contractor. But we’re confident the project would be finished on time.

Total incompetence.


10.) 26 Jun 2024
26 Jun 2024 18:03:25
That makes no sense at all tbh.


11.) 26 Jun 2024
26 Jun 2024 21:02:10
Did a Celtic fan tell you this story aye nonsense.